5 questions will be shown from a total of 30 free practice questions to prepare you for the PMP exam. Enjoy!
1 / 5
1. A project manager submits a version of the software that the project team created. During the review meeting, a team member informs the project manager of a recent regulation that requires a dual verification process in the software. However, the product sponsor strongly insists there should be no updates to the software. What should the project manager do?
2 / 5
2. A hybrid project is experiencing several issues with both the agile delivery of the product as well as the predictive development of a marketing strategy. What should the project manager do to receive feedback from stakeholders located in different time zones?
3 / 5
3. A project is behind schedule due to an incorrectly estimated task on the critical path. What should the project manager do?
4 / 5
4. After completion of a project with specific users in various countries, the project manager’s supervisor asks if the project users are satisfied with the way the project was run. What two actions should the project manager take? (Choose two)
5 / 5
5. During the implementation phase of a construction project the customer asked a key subcontractor to deliver a work package ahead of time. The subcontractor was not prepared for it and asked the project manager for additional budget. What should the project manager do first?
Your score is
The average score is 40%
Practice Again
More IT practice tests CLICK HERE
More IT practice tests
CLICK HERE