5 questions will be shown from a total of 30 free practice questions to prepare you for the PMP exam. Enjoy!
1 / 5
1. Five agile teams working together on a product recently performed release planning Midway through the project, each team showed that their progress was on track. When all of the teams integrated at the product level, many integration issues were observed. The overall product release progress declined with predictions showing the committed content will not be able to be accomplished. What should the project manager have done differently?
2 / 5
2. During a network upgrade for a company, the client informs the project manager that a government representative notified the client about a separate project that will affect the network upgrade. Any change in the upgrade will impact the project’s cost and schedule. What should the project manager do first?
3 / 5
3. A team has different ideas on how to address a feature of a product under construction and; although the sprint began two days ago, they have still not reached a consensus. What should the project manager do?
4 / 5
4. A leader from project B consistently reaches out to a team member in project A for assistance. What should project A’s project manager do?
5 / 5
5. A team is given an agile project to build a conceptual product for a new customer. While planning, the project manager is trying to determine the best way to show value to the customer, as the technical requirements are not very detailed. What should the project manager do to help the client understand the value delivered during project execution?
Your score is
The average score is 40%
Practice Again
More IT practice tests CLICK HERE
More IT practice tests
CLICK HERE