5 questions will be shown from a total of 30 free practice questions to prepare you for the PMP exam. Enjoy!
1 / 5
1. A project manager is implementing a new software system. Some department staff members are questioning the necessity of the change and feel the new system will impede their current processes. What should the project manager have done at the start of the project to prevent this resistance?
2 / 5
2. A project manager submits a version of the software that the project team created. During the review meeting, a team member informs the project manager of a recent regulation that requires a dual verification process in the software. However, the product sponsor strongly insists there should be no updates to the software. What should the project manager do?
3 / 5
3. A project manager is appointed for the deployment of a new solution. The solution will be integrated into the environment by a third-party vendor. This vendor just announced a delay in delivering a key component, which will impact the project schedule. What should the project manager do?
4 / 5
4. Early in the execution phase, a project manager discovers that recent changes in enterprise environmental factors (EEFs) will severely reduce the implementation cost and shorten the project schedule. How should the project manager address this situation?
5 / 5
5. Organizational downsizing has resulted in the key subject matter expert (SME) resource leaving a multiyear project. What should the project manager do?
Your score is
The average score is 40%
Practice Again
More IT practice tests CLICK HERE
More IT practice tests
CLICK HERE