5 questions will be shown from a total of 30 free practice questions to prepare you for the PMP exam. Enjoy!

1 / 5

1. An external project manager is managing the construction of new corporate offices for a large company. The project management plan states that it is necessary to contract a highly trained external resource to revise and validate an important project component. The client has rejected hiring the external resource because of the high cost even though it is within the project budget. What should the project manager do to resolve this issue?

2 / 5

2. During the implementation phase of a construction project the customer asked a key subcontractor to deliver a work package ahead of time. The subcontractor was not prepared for it and asked the project manager for additional budget. What should the project manager do first?

3 / 5

3. A project manager receives a serious complaint from a functional manager about a team member. What should the project manager do?

4 / 5

4. In a hybrid project, 100 new base stations are being added to a 4G mobile network every month. At the end of the first month, the team is behind the target and the operator is losing money. The stakeholders are requesting information on when the base stations can go live and begin to bill. What should the project manager do to take the schedule back and accelerate the return on investment (ROI) of the project?

5 / 5

5. A hybrid project is experiencing several issues with both the agile delivery of the product as well as the predictive development of a marketing strategy. What should the project manager do to receive feedback from stakeholders located in different time zones?