登入開始練習

0%
0 votes, 0 avg

5 questions will be shown from a total of 30 free practice questions to prepare you for the PMP exam. Enjoy!

1 / 5

1. Five agile teams working together on a product recently performed release planning Midway through the project, each team showed that their progress was on track. When all of the teams integrated at the product level, many integration issues were observed. The overall product release progress declined with predictions showing the committed content will not be able to be accomplished.
What should the project manager have done differently?

2 / 5

2. A project manager is managing a project which has a very complex and long execution period Although the project is mostly predictive, the team was able to break the design and execution into smaller packages using a hybrid framework. The business wants to keep track of the value delivered by this framework application but there is no defined set of measurable items for the framework.
What should the project manager do first?

3 / 5

3. Early in the execution phase, a project manager discovers that recent changes in enterprise environmental factors (EEFs) will severely reduce the implementation cost and shorten the project schedule. How should the project manager address this situation?

4 / 5

4. After completion of a project with specific users in various countries, the project manager’s supervisor asks if the project users are satisfied with the way the project was run. What two actions should the project manager take? (Choose two)

5 / 5

5. A project manager receives a serious complaint from a functional manager about a team member. What should the project manager do?

Free sign-up(click) to

1. skip this part 2. access all free questions 3. show explanations

Your score is

The average score is 40%

0%

立即開始14天免費使用PMP模擬考題練習

更多資訊:PMP (Project Management Professional) 考試前必須知道的 20 個公式和概念+免費PMP試題練習[2022]

腦海中有大膽的想法嗎

分享內容並留言吧