登入開始練習

0%
0 votes, 0 avg

5 questions will be shown from a total of 30 free practice questions to prepare you for the PMP exam. Enjoy!

1 / 5

1. A leader from project B consistently reaches out to a team member in project A for assistance.
What should project A’s project manager do?

2 / 5

2. A project team with members from many different countries is struggling to cooperate. The project manager accepted these difficulties during the storming phase of team development, but the team has not moved to the next phase. The project is beginning to fall behind schedule.
What can the project manager do to move the team to the norming phase?

3 / 5

3. A team has different ideas on how to address a feature of a product under construction and; although the sprint began two days ago, they have still not reached a consensus. What should the project manager do?

4 / 5

4. A client verbally approves the project management plan. What should the project manager do first?

5 / 5

5. The main project stakeholder was fired and replaced by another stakeholder. The new stakeholder reviewed the project scope and requested numerous changes, arguing that the stakeholder’s team is unhappy with the results to date.
What should the project manager do?

Free sign-up(click) to

1. skip this part 2. access all free questions 3. show explanations

Your score is

The average score is 40%

0%

立即開始14天免費使用PMP模擬考題練習

更多資訊:PMP (Project Management Professional) 考試前必須知道的 20 個公式和概念+免費PMP試題練習[2022]

腦海中有大膽的想法嗎

分享內容並留言吧