登入開始練習

0%
0 votes, 0 avg

5 questions will be shown from a total of 30 free practice questions to prepare you for the PMP exam. Enjoy!

1 / 5

1. A project manager has noticed that a critical team member is consistently arguing with a client. This has started to have a negative effect on the meetings.
How should the project manager address this?

2 / 5

2. During the implementation phase of a construction project the customer asked a key subcontractor to deliver a work package ahead of time. The subcontractor was not prepared for it and asked the project manager for additional budget. What should the project manager do first?

3 / 5

3. A group has been working together for one month. During daily meetings a team member continues to express issues in completing their tasks.
What should the project manager do?

4 / 5

4. Organizational downsizing has resulted in the key subject matter expert (SME) resource leaving a multiyear project. What should the project manager do?

5 / 5

5. A leader from project B consistently reaches out to a team member in project A for assistance.
What should project A’s project manager do?

Free sign-up(click) to

1. skip this part 2. access all free questions 3. show explanations

Your score is

The average score is 40%

0%

立即開始14天免費使用PMP模擬考題練習

更多資訊:PMP (Project Management Professional) 考試前必須知道的 20 個公式和概念+免費PMP試題練習[2022]

腦海中有大膽的想法嗎

分享內容並留言吧