5 questions will be shown from a total of 30 free practice questions to prepare you for the PMP exam. Enjoy!
1 / 5
1. A project manager is managing a project which has a very complex and long execution period Although the project is mostly predictive, the team was able to break the design and execution into smaller packages using a hybrid framework. The business wants to keep track of the value delivered by this framework application but there is no defined set of measurable items for the framework. What should the project manager do first?
2 / 5
2. During the implementation phase of a construction project the customer asked a key subcontractor to deliver a work package ahead of time. The subcontractor was not prepared for it and asked the project manager for additional budget. What should the project manager do first?
3 / 5
3. Five agile teams working together on a product recently performed release planning Midway through the project, each team showed that their progress was on track. When all of the teams integrated at the product level, many integration issues were observed. The overall product release progress declined with predictions showing the committed content will not be able to be accomplished. What should the project manager have done differently?
4 / 5
4. A project manager completes a project management plan for a global project due in 12 months. When two team members leave the project, what should the project manager do?
5 / 5
5. A leader from project B consistently reaches out to a team member in project A for assistance. What should project A’s project manager do?
Your score is
The average score is 40%
Practice Again
腦海中有大膽的想法嗎分享內容並留言吧
腦海中有大膽的想法嗎