1. During a network upgrade for a company, the client informs the project manager that a government representative notified the client about a separate project that will affect the network upgrade. Any change in the upgrade will impact the project’s cost and schedule. What should the project manager do first?
2 / 5
2. A team has different ideas on how to address a feature of a product under construction and; although the sprint began two days ago, they have still not reached a consensus. What should the project manager do?
3 / 5
3. The main project stakeholder was fired and replaced by another stakeholder. The new stakeholder reviewed the project scope and requested numerous changes, arguing that the stakeholder’s team is unhappy with the results to date. What should the project manager do?
4 / 5
4. In a hybrid project, 100 new base stations are being added to a 4G mobile network every month. At the end of the first month, the team is behind the target and the operator is losing money. The stakeholders are requesting information on when the base stations can go live and begin to bill. What should the project manager do to take the schedule back and accelerate the return on investment (ROI) of the project?
5 / 5
5. A project manager receives a serious complaint from a functional manager about a team member. What should the project manager do?